Standard Field Mappings

Acumen includes standard field mappings for each of the supported platforms.

These are listed below. You can create additional custom field mappings using the Fields tab.

Acumen Field IPMDAR Microsoft Project / Project Server Primavera P6 Primavera Risk Deltek Cobra Deltek Open Plan UN/CEFACT Safran
Activity Status Calculated Status Activity Status Calculated NA Progress Type Calculated NA
Activity Type TaskTypeID Calculated Activity Type Task Type Calculated Activity Type ProjectScheduleTask.TypeCode Calculated
Actual Cost NA Actual Cost Calculated Cost[Actual] NA Calculated NA Calculated
Actual Duration Calculated Actual Duration Actual Duration NA NA NA NA Calculated
Actual Finish ActualFinishDate Actual Finish Actual Finish Actual Finish NA Actual Finish ActualScheduledBasePeriod.Finish Calculated
Actual Start ActualStartDate Actual Start Actual Start Actual Start NA Actual Start ActualScheduledBasePeriod.Start Calculated
ACWP (AC) NA ACWP ACWP ACWP (AC) NA NA
Baseline Finish BaselineFinishDate Baseline Finish Planned Finish Baseline Finish NA Baseline Finish TargetScheduledBasePeriod.Finish Baseline Early Finish
Baseline Start BaselineStartDate Baseline Start Planned Start Baseline Start NA Baseline Start TargetScheduledBasePeriod.Start Baseline Early Start
Baseline Work NA Baseline Work Budgeted Labor Units Calculated NA NA NA NA
BCWP (EV) NA BCWP BCWP (EV) Calculated BCWP (EV) Calculated NA NA
BCWS (PV) NA BCWS Calculated NA BCWS (PV) NA NA NA
Budget Cost NA Baseline Cost Calculated Cost[Budget] NA Calculated NA NA
CAM-EAC NA NA NA NA CAM-EAC NA NA NA
Critical OnCriticalPath Critical Critical Critical NA Critical_Activity ProjectScheduleTask.CriticalPathIndicator Calculated
Description Name Name Activity Name Description Description Activity Desc. ProjectScheduleTask.Description Description
EAC NA EAC EAC NA EAC NA NA NA
Early Finish EarlyFinishDate Early Finish Early Finish Early Finish NA Early Finish EarliestScheduledBasePeriod.Finish NA
Early Start EarlyStartDate Early Start Early Start Early Start NA Early Start EarliestScheduledBasePeriod.Start Early Start
ETC NA NA NA NA ETC NA NA NA
Finish CurrentFinishDate Finish Finish Finish Calculated Early Finish CurrentScheduledBasePeriod.Finish Calculated
Free Float FreeFloatDuration Free Float Free Float Free Float NA Free Float Free Float Free Float
ID ID ID Activity ID ID ID Activity ID ProjectScheduleTask.Name Activity Name
Late Start LateStartDate Late Start Late Start Late Start NA Late Start Late Start Late Start
Late Finish LateFinishDate Late Finish Late Finish Late Finish NA Late Finish Late Finish Late Finish
LIKELY NA NA NA NA LIKELY NA NA NA
Longest Path OnDrivingPath Critical Longest Path Critical NA Critical NA Calculated
MOD NA NA NA NA MOD NA NA NA
Number of Lags Calculated Calculated Calculated Calculated NA Calculated ProjectScheduleTaskRelationship.LagTimeMeasure NA
Number of Leads Calculated Calculated Calculated Calculated NA Calculated Calculated NA
Number of FF Predecessors Calculated Calculated Calculated Calculated NA Calculated Calculated NA
Number of Predecessors Calculated Calculated Calculated Calculated NA Calculated Calculated NA
Number of SF Predecessors Calculated Calculated Calculated Calculated NA Calculated Calculated NA
Number of SS Predecessors Calculated Calculated Calculated Calculated NA Calculated Calculated NA
Number of Successors Calculated Calculated Calculated Calculated NA Calculated Calculated NA
Original Duration CurrentDuration Duration Original Duration Original Duration NA Original Duration TotalDurationMeasure Duration
OBS OBSElementID
OTB NA NA NA NA OTB NA NA NA
P50 Cost NA NA NA P50 Cost NA NA NA NA
P50 Finish NA NA NA P50 Finish NA NA NA NA
P50 Start NA NA NA P50 Start NA NA NA NA
P80 Cost NA NA NA P80 Cost NA NA NA NA
P80 Finish NA NA NA P80 Finish NA NA NA NA
P80 Start NA NA
Percent Complete CalculatedPercentComplete % Complete Calculated Percent Complete NA Calculated ProjectScheduleTask.CalculatedCompletionPercent NA
Physical % Complete PhysicalPercentComplete
PLAN_ACC NA NA NA NA PLAN_ACC NA NA NA
Primary Constraint TaskConstraints. ConstraintTypeID Constraint Type Primary Constraint Primary Constraint NA Calculated Primary Constraint Calculated
Primary Constraint Date TaskConstraints. ConstraintDate Constraint Date Primary Constraint Date Primary Constraint Date NA Calculated Primary Constraint Date Calculated
Project Finish ProjectScheduleData. CurrentFinishDate Finish Date Finish Data Date NA Scheduled Finish NA NA
Project Start ProjectScheduleData. CurrentStartDate Start Date Start Start NA Project Start NA NA
Project Time Now ProjectScheduleData .StatusDate Status Date Data Date Finish NA Time Now NA NA
Remaining Cost NA Remaining Cost Calculated Cost[Remaining] NA ETC NA Calculated
Remaining Duration RemainingDuration Remaining Duration Remaining Duration Remaining Duration NA Computed Remaining Dur. ProjectScheduleTask.RemainingDurationMeasure Remaining Duration Analyzed
REPLAN NA NA NA NA REPLAN NA NA NA
Risk Input - Duration Description NA NA NA Calculated NA NA NA
Risk Input - Duration LowerPcent NA NA NA Calculated NA NA NA NA
Risk Input - Duration Max NA NA NA Risk Input - Duration Maximum NA NA NA NA
Risk Input - Duration Mean NA NA NA Risk Input - Duration Mean NA NA NA NA
Risk Input - Duration Min NA NA NA Risk Input - Duration Minimum NA NA NA NA
Risk Input - Duration MostLikely NA NA NA Risk Input - Duration MostLikely NA NA NA NA
Risk Input - Duration MostlikelyPcent NA NA NA Calculated NA NA NA NA
Risk Input - Duration Notes NA NA NA Risk Input - Duration Notes NA NA NA NA
Risk Input - Duration Risk Distribution NA NA NA Calculated NA NA NA NA
Risk Input - Duration RiskFunction NA NA NA Calculated NA NA NA NA
Risk Input - Duration RiskId NA NA NA Calculated NA NA NA NA
Risk Input - Duration RiskOn NA NA NA Calculated NA NA NA NA
Risk Input - Duration Shape NA NA NA Calculated NA NA NA NA
Risk Input - Duration StdDeviation NA NA NA Calculated NA NA NA NA
Risk Input - Duration UpperPcent NA NA NA Calculated NA NA NA NA
Risk Input - Probabilistic Description NA NA NA Calculated NA NA NA NA
Risk Input - Probabilistic Notes NA NA NA Calculated NA NA NA NA
Risk Input - Probabilistic RiskFunction NA NA NA Calculated NA NA NA NA
Risk Input - Probabilistic RiskId NA NA NA Calculated NA NA NA NA
Risk Input - Probabilistic RiskOn NA NA NA Calculated NA NA NA NA
Risk Input - Probabilistic Links Description NA NA NA Calculated NA NA NA NA
Risk Input - Probabilistic Links Notes NA NA NA Risk Input - Probabilistic Links Notes NA NA NA NA
Risk Input - Probabilistic Links RiskFunction NA NA NA Calculated NA NA NA NA
Risk Input - Probabilistic Links RiskId NA NA NA Calculated NA NA NA NA
Risk Input - Probabilistic Links RiskOn NA NA NA Calculated NA NA NA NA
Risk Input - Task Existence Description NA NA NA Calculated NA NA NA NA
Risk Input - Task Existence Notes NA NA NA Risk Input - Task Existence Notes NA NA NA NA
Risk Input - Task Existence RiskFunction NA NA NA Risk Input - Task Existence Function NA NA NA NA
Risk Input - Task Existence RiskId NA NA NA Calculated NA NA NA NA
Risk Input - Task Existence RiskOn NA NA NA Calculated NA NA NA NA
Risk Input - Task Existence Probability NA NA NA Risk Input - Task Existence NA NA NA NA
Risk Output - CostSensitivity NA NA NA Risk Output - CostSensitivity NA NA NA NA
Risk Output - CostStdDeviation NA NA NA Risk Output - CostStdDeviation NA NA NA NA
Risk Output - CriticalityIndex NA NA NA Risk Output - CriticalityIndex NA NA NA NA
Risk Output - DurationCruciality NA NA NA Risk Output - Duration Cruciality NA NA NA NA
Risk Output - DurationStdDeviation NA NA NA Risk Output - DurationStdDeviation NA NA NA NA
Risk Output - DurationSensitivity NA NA NA Risk Output - DurationSensitivity NA NA NA NA
Risk Output - MeanCost NA NA NA Risk Output - MeanCost NA NA NA NA
Risk Output - MeanDuration NA NA NA Risk Output - MeanDuration NA NA NA NA
Risk Output - MeanFinish NA NA NA Risk Output - MeanFinish NA NA NA NA
Risk Output - MeanStart NA NA NA Risk Output - MeanStart NA NA NA NA
Risk Output - PercentageTaskExisted NA NA NA Risk Output - % Iterations Existed NA NA NA NA
Risk Output - ScheduleSensitivityIndex NA NA NA Risk Output - ScheduleSensitivityIndex NA NA NA NA
Secondary Constraint TaskConstraints. ConstraintTypeID NA Secondary Constraint NA NA Calculated Secondary Constraint Calculated
Secondary Constraint Date TaskConstraints. ConstraintDate NA Secondary Constraint Date NA NA Calculated Secondary Constraint Date Calculated
Start CurrentStartDate Start Start Start Start Early Start CurrentScheduledBasePeriod.Start Calculated
Total Cost NA Cost Calculated Cost[Total] NA Calculated NA NA
Total Float TotalFloatDuration Total Slack Total Float TotalFinshFloat NA Total Float ProjectScheduleTask.TotalFloatDurationMeasure Total Float
WBS Code WBSElementID Outline Number WBS Work Breakdown Structure WBS Code NA NA NA
WBS Name NA (unless IPMDAR Cost is loaded) Outline Number WBS Name Work Breakdown Structure WBS Name NA NA NA
WORST NA NA NA NA WORST NA NA NA